橋梁伸縮縫安裝前期的施工準備工作
1.伸縮縫預留槽的設置:橋面鋪裝混凝土施工前,伸縮縫應用塑料泡沫板填實,防止混凝土等廢棄物掉入,影響伸縮裝置的性能;橋面鋪裝施工后,伸縮縫預留槽口應用低標號砂漿或混凝土填充至與橋面齊平,以保證表面瀝青混凝土鋪裝的平整度,防止施工時預留鋼筋受壓變形,影響伸縮裝置的安裝。
2.伸縮縫預留槽的開挖:瀝青混凝土上層完成后,即可進行伸縮縫開槽。首先,根據設計寬度,在表層放出切割邊緣標記??梢韵扔盟驖癖韺?,然后用膠帶紙沿切割標線在伸縮縫兩側貼上塑料薄膜,再蓋上一層硬塑料編織布,防止切割過程中污染路面。技術工人操作切割機沿標準線切割,保證切割縫整齊順直。切割完成后,手動去除表面混合物。對于剩余凹槽內的填充物,可先用風鎬將其打碎,然后用人工清除。 and care should be taken to prevent the corner of the slit from being damaged. Check whether the cement concrete under the asphalt concrete in the tank is dense. If it is suspended, it should be cut again along the standard line until the inner walls on both sides of the tank are flat and dense. The concrete surface in the tank is treated by manual roughening. Check whether the reserved reinforcement in the groove meets the design and installation requirements, especially the reserved reinforcement at the plate end, which is deformed during the prefabrication, transportation and installation of the beam and slab, adjust the reserved reinforcement that does not meet the requirements, and remove the concrete laitance attached to the surface of the reinforcement. Clean up the residue in the tank and check whether the plastic foam board in the seam is complete and continuous, 以及縫寬是否符合設計要求。預留槽可以用水槍徹底清洗干凈。
衡水德越工程橡膠訂購熱線:趙經理(微信同步)